Neighborhood Drainage Improvements
Back to Projects
Neighborhood Drainage Improvements
In ProgressAt RiskPRJ-011 ยท Mobile Public Works Department
Project Information
- Project ID
- PRJ-011
- Grantee
- Mobile Public Works Department
- Project Type
- Drainage Infrastructure
- Phase
- In Progress
- Status
- At Risk
- Risk Level
- Medium
- Start Date
- Feb 15, 2027
- Est. Completion
- Oct 31, 2028
- Assigned Manager
- Angela Reyes
- Open Findings
- 1
Permitting delayed due to revised floodplain mapping requirements.
Budget Summary
Total Budget
$3,200,000
Committed
$3,200,000
Drawn
$960,000
Remaining
$2,240,000
Percent Drawn30%
Project Progress
Project Initiation
Feb 15, 2027
Environmental Review
Cleared
HEROS Clearance
Complete
In Progress
Feb 15, 2027
Estimated Completion
Oct 31, 2028
Next Milestones
Permitting submittal
Due: Jul 10, 2027
Recent Documents
No documents uploaded for this project.
Risk Summary
| Finding | Severity | Status |
|---|---|---|
| Revised floodplain analysis required before permit submittal | Medium | In Progress |
Assigned Team
AR
Angela Reyes
Project Manager
AC