Drawdowns & Budget

Total Drawn This Quarter

$1,420,000

Requests Submitted

8

Approved

3

Pending Review

4

Denied / Returned

1

Draw Request Status

All draw requests by status

Drawdown Trend

Cumulative drawdown activity

Program Budget Summary

Total Allocation

$50,000,000

Total Drawn

$20,750,000

Remaining

$29,250,000

Budget vs. Drawn by Project

ProjectBudgetDrawnRemaining% Drawn
Smith Community Center$6,200,000$3,100,000$3,100,000
50%
West Mobile Housing Rehabilitation$5,800,000$2,320,000$3,480,000
40%
Bayview Infrastructure Improvements$4,500,000$1,350,000$3,150,000
30%
MLK Public Improvements$3,800,000$2,090,000$1,710,000
55%
Oakleigh Park Upgrades$2,900,000$435,000$2,465,000
15%
Africatown Community Facility$5,200,000$2,860,000$2,340,000
55%
Downtown Streetscape Improvements$4,100,000$1,230,000$2,870,000
30%
Gulf Village Housing Stabilization$4,800,000$480,000$4,320,000
10%
Toulminville Resilience Project$3,500,000$525,000$2,975,000
15%
Mobile Workforce Training Center$4,200,000$3,780,000$420,000
90%
Neighborhood Drainage Improvements$3,200,000$960,000$2,240,000
30%
Senior Wellness Facility$1,800,000$1,620,000$180,000
90%

Recent Draw Requests

Request IDProjectAmountSubmittedQuarterStatusDocumentation
DR-001Smith Community Center$620,000Jun 1, 2027Q3 FY27ApprovedComplete
DR-002Smith Community Center$480,000May 1, 2027Q2 FY27ApprovedComplete
DR-003West Mobile Housing Rehabilitation$580,000Jun 15, 2027Q3 FY27PendingUnder Review
DR-004MLK Public Improvements$380,000Jun 20, 2027Q3 FY27ReturnedIncomplete
DR-005Africatown Community Facility$520,000Jun 10, 2027Q3 FY27ApprovedComplete
DR-006Mobile Workforce Training Center$420,000May 20, 2027Q2 FY27ApprovedComplete
DR-007Senior Wellness Facility$180,000Jun 25, 2027Q3 FY27PendingUnder Review
DR-008Bayview Infrastructure Improvements$350,000Apr 15, 2027Q2 FY27ApprovedComplete
DR-009Downtown Streetscape Improvements$280,000Jun 5, 2027Q3 FY27ApprovedComplete
DR-010Neighborhood Drainage Improvements$240,000May 10, 2027Q2 FY27DeniedIncomplete
DR-011MLK Public Improvements$290,000Mar 20, 2027Q1 FY27ApprovedComplete
DR-012West Mobile Housing Rehabilitation$450,000Apr 1, 2027Q2 FY27ApprovedComplete
DR-013Oakleigh Park Upgrades$145,000Jun 18, 2027Q3 FY27PendingUnder Review
DR-014Gulf Village Housing Stabilization$120,000May 25, 2027Q2 FY27ReturnedIncomplete
DR-015Toulminville Resilience Project$175,000Jun 22, 2027Q3 FY27PendingUnder Review